On December 11, 2020, it was conducted a monitoring visit for the project KALCEA (Knowledge Triangle for a Low Carbon Economy)
Status of the project:
- All WP1 deliverables will be completed by June 30th 2021.
- WP2 has started; a coordination meeting is developed on June 18th 2021.
- Staff training workshops (WP3) have started earlier than planned and will continue throughout the project. Next
staff training activity (online) planned for June 28th 2021: the CROSSBOW project. - Equipment (WP3). Detailed specifications for equipment will be finalized by July 15th, 2021. Tenders to be issued
in September 2021, 7 months earlier than planned. - Local dissemination (WP6) activities will be planned until December 20th, 2021.